QUESTION 98
You are required to migrate your 11.2.0.3 database as a pluggable database (PDB) to a multitenant container database (CDB).
The following are the possible steps to accomplish this task:
1. Place all t he user-defined tablespace in read-only mode on t he source database.
2. Upgrade the source database to a 12c version.
3. Create a new PDB in t he target container database.
4. Perform a full transportable export on t he source database with t he VERSION parameter set to 12 using the expdp utility.
5. Copy the associated data files and export t he dump file to the desired location in the target database.
6. Invoke the Data Pump import utility on t he new PDB database as a user with the DATAPUMP_IMP_FULL_DATABASE role and specify the full transportable import options.
7. Synchronize the PDB on t he target container database by using the DBMS_PDS.SYNC_ODB function.
Identify the correct order of the required steps.
A. 2, 1, 3, 4, 5, 6
B. 1, 3, 4, 5, 6, 7
C. 1, 4, 3, 5, 6, 7
D. 2, 1, 3, 4, 5, 6, 7
E. 1, 5, 6, 4, 3, 2
Correct Answer: C